The Project Process at Western Kentucky University
- Pre-Planning - We will meet with you regarding the following:
- Needs assessment
- Program definition
- Site Selection
- Feasibility Study
- Environmental Study
- Project Development - How we proceed with your project:
- Architect Selection
- Technical proposal
- Fee negotiation
- Project Design
- Schematic (30%)
- Design develeopment (60%)
- Contract documents (90%)
- Final review/estimates
- Code reveiw
- Issue requests for bid
|
|
|
| |
About Us
|
|
|
|
| |
Meet the Staff
|
|
|
|
| |
Our Location
|
|
|
|
| |
On-Line Forms
|
|
|
|
| |
Design Standards
|
|
|
|
| |
Permitting
|
|
|
|
| |
Plan Review
|
|
|
|
| |
Project Status
|
|
|
|
| |
Opportunities for Architects, Engineers & Contractors
|
|
|
|
| |
Construction on Campus
|
|
|
|
| |
Contact Us
|
|
|
|
| |
|
|
|
- Construction - What will happen?
- Receive Bids/Award Bid (negotiation)
- Pre-construction meeting
- Site coordination/mobilization
- Submittals/material delivery
- Construction Management
- Field verification/testing
- Schedule tracking/payments
- RFI/Field changes
- Contract changes
- Change orders
- Time extensions
- Project Closeout/Startup - When you're close to occupancy!
- Final Inspection/Punch List/Liquidated Damages
- Furnishings, fixtures, equipment
- Startup,testing, documentation
- As builts
- Operations manuals
- Balance reports
- Warranties/guarantees
- Commissioning (formal process)
- Final clean up
- Move-in/Ribbon-cutting/Dedication
- Voice/video/data
- Touch-ups/equipment adjustments, etc.
- Building Operations
- Establish maintenance and cleaning schedules and budgets
- Warranty calls
- Post occupancy evaluation
- Create capital renewal fund